MANGAN, 08 Oct: The road over Lanthey khola on the Mangan-Chungthang axis where around 80 metres of road formation was washed out by a landslide triggered by heavy rainfall on 19 September will take at least another five days to be restored, if the weather permits.
Two excavators have been deployed on both sides of the slide for restoration work, however, continuous fall of debris is delaying work at the site. Meanwhile, some transshipment of essential food items is being carried out at this spot. A ropeway has also been set up here to transship heavy loads and essentials across.
BRO officials at the spot point out that speculations on by when the road here will be restored are futile since every shower wipes out the repairs.
It may be mentioned here that the Lanthey slide was one of the most troublesome spots on the North Sikkim Highway for the past 20 years but had been holding up for the last few years until it collapsed fresh on 19 Sept.
Meanwhile, the Army Engineering Division has constructed a bridge at Chyandara slide near Singhik just half a kilometre ahead of Lanthey Khola as this spot too was washed out by a landslide on the same evening. The traffic here resumed on 05 October.
Thanks for the valuable information. Is all of North Sikkim inaccessible or I can still visit at least a few areas?
ReplyDelete