MG-NREGA Social Audit conducted at Kabi-Tingda GVK
GANGTOK, 12 Aug: The MG-NREGA Social Audit of Lingdok-Nampong GPK and Navey-Shotak GPK under Kabi-Tingda GVK was conducted on 07 and 09 August 2014 by District Resource Institution (North District) Nava Jyoti Sangh under the guidance of Social Audit Unit (SAU)-Sikkim with support from Rural Management and Development Department (RM&DD),Govt. of Sikkim.
A press release informs that under Lingdok-Namphok GPK, 48 MG-NREGA works were audited which includes 28 land development works, 5 Minor irrigation channel works, 1 water harvesting work and 9 Eco-friendly footpath works.
Total amount of Rs.1,99,02,033 was sanctioned under MG-NREGA, out of which Rs. 1,07,42,718 was audited. On the other hand under Navey-Shotak GPK, 69 MG-NREGA works were audited which includes 54 land development works, 4 Eco-friendly footpath works, 4 protective wall works, 2 Construction of concrete footpath works, 2 Jhora training works and 3 Box drain works.
Total amount of Rs.1,38,87,600 was sanctioned under MG-NREGA, out of which Rs. 1,01,25,759 was audited under Navey-Shotak GPK, the release adds.
GANGTOK, 12 Aug: The MG-NREGA Social Audit of Lingdok-Nampong GPK and Navey-Shotak GPK under Kabi-Tingda GVK was conducted on 07 and 09 August 2014 by District Resource Institution (North District) Nava Jyoti Sangh under the guidance of Social Audit Unit (SAU)-Sikkim with support from Rural Management and Development Department (RM&DD),Govt. of Sikkim.
A press release informs that under Lingdok-Namphok GPK, 48 MG-NREGA works were audited which includes 28 land development works, 5 Minor irrigation channel works, 1 water harvesting work and 9 Eco-friendly footpath works.
Total amount of Rs.1,99,02,033 was sanctioned under MG-NREGA, out of which Rs. 1,07,42,718 was audited. On the other hand under Navey-Shotak GPK, 69 MG-NREGA works were audited which includes 54 land development works, 4 Eco-friendly footpath works, 4 protective wall works, 2 Construction of concrete footpath works, 2 Jhora training works and 3 Box drain works.
Total amount of Rs.1,38,87,600 was sanctioned under MG-NREGA, out of which Rs. 1,01,25,759 was audited under Navey-Shotak GPK, the release adds.