| Sludge from Adit-III tunnel bypasses the treatment tank to empty directly into Rangit at Rohtak in West Sikkim where Rangit Stage-IV hydel project is under development |
ANAND OBEROI
GANGTOK, 01 March: The inspection team from the West District administration and the State Pollution Board [SPCB], which visited the Adit-II tunnel site of Rangit Stage- IV hydroelectric project at Rothak, West Sikkim, this afternoon has given a “temporary go-ahead” to the project developer to resume work at the site. The DC [West], it may be recalled, had directed that work be stopped when it was discovered that the project developer was dumping untreated sludge [extracted from the tunnel excavation] into the Rangit [click here for details].
Coastal Project Pvt.Ltd, contracted by Jal Power Development Corporation working at the project site had been show-caused by the Department of Forests and the West district administration for “illegally dumping untreated waste” from the tunnels into the Rangit river.