SPECIAL FOCUS: The PMGSY Road Trouble at Lower Parbing
SUBASH RAI
GANGTOK, 14 Mar: Lack of proper planning by the concerned officials is the main shortcoming leading to the problems being suffered due to the Lower Barbing PMGSY road construction project. The under construction road from Ranka Rai Gaon to Rey Khola Swimming Pool area has become a hazard for the villagers as they are witnessing irreparable loss to their properties. The contractor assigned the job is also suffering problems because the villagers there are threatening to stop the work if the destruction continues.
The problem surfaced in the first week of February when phase-II of the construction started. It was Namgyal Bhutia, a resident, who first noticed that the alignment of the road was not following the original survey which had been endorsed by all villagers. [for background details, click here, here and here]
SUBASH RAI
GANGTOK, 14 Mar: Lack of proper planning by the concerned officials is the main shortcoming leading to the problems being suffered due to the Lower Barbing PMGSY road construction project. The under construction road from Ranka Rai Gaon to Rey Khola Swimming Pool area has become a hazard for the villagers as they are witnessing irreparable loss to their properties. The contractor assigned the job is also suffering problems because the villagers there are threatening to stop the work if the destruction continues.
The problem surfaced in the first week of February when phase-II of the construction started. It was Namgyal Bhutia, a resident, who first noticed that the alignment of the road was not following the original survey which had been endorsed by all villagers. [for background details, click here, here and here]